Scheduled maintenance - IaaS / Hosting Cluster 02 and 06 from March 29th 07.00 to the 30th 22.00

Scheduled Maintenance Report for Cloud Factory A/S

Completed

The scheduled maintenance has been completed.
Posted Mar 30, 2025 - 23:00 CEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 29, 2025 - 07:00 CET

Scheduled

Dear partner

Here's a little info on the scheduled maintenance of our IaaS platform from March 29th 07.00 to the 30th 22.00

What's the maintenance about?
We will update the software on our Nutanix platform, Cluster 02 and 06 between Saturday the 29th 07.00 and Sunday the 30th 22.00 of March.
If you want a list of your customers and Virtual Machines located on Cluster 02 and 06, please get in touch with us at support@cloudfactory.dk.

Risk assessment:
According to our evaluation, the risk is low.
Nutanix fully automates the upgrade, and we are following the procedures from Nutanix.
Release notes and compatibility is checked and is approved.
The software upgrade was tested OK on a test platform.

Impact:
When the upgrade starts, 1 cluster node at a time will be drained, and the running Virtual Machines will be moved to another host. VM’s are moving around between hosts daily, there is no reason to think this will be noticeable.
Estimated downtime: none

Fallback plan:
During the upgrade, only 1 cluster node is offline at a time and if that node experiences a failure, the upgrade process will halt automatically. In such an event, Nutanix support will be engaged to address the issue.

We will send out notifications before the maintenance and after completion as well.
If you have any questions, please get in touch with us at support@cloudfactory.dk

Best regards
Cloud Factory team
Posted Mar 10, 2025 - 15:37 CET